The Build

The first job for our installers, Homeco Energy, once the scaffolding was up, was to install the inverters. The site required 3 in total.

Inverters

 

After this the frames for the panels were installed and then the panels and wiring were laid.

 

Picture1

Picture2

Picture3

roof shot

Once the panels were installed, the cabling was routed in to the building, as shown below. These are big cables, so this was not a straight forward task!

Picture5

After the installation was complete, we had to wait for the District Network Operator to approve the installation and connect it to the grid. We are now generating electricity at the site and you will soon be able to see live generation figures from the site.